Aberdeen City Centre & Beach Master Plan Update – Week Commencing 14 October 2024

Project Works – Union Street Central 

The east section carrier drain has been installed. Unknown utilities and buried structures meant additional work to negotiate obstructions. Two bus shelters on east section now removed. Existing granite kerbs from east section being retained for reuse elsewhere by Aberdeen City Council roads staff. Suitable existing Caithness paving slabs on east section being retained for reuse on Market project. New kerbs, granite setts and slabs have been delivered to project storage compound ready for installation.

 

Project Works – Market

Structural alterations to 91-93 Union Street underway with removal of protruding concrete sections on East Green elevations. Internal crash deck under construction ahead of removal of Union Street floor slab and concrete beams. Cutting underway on existing concrete slab and retaining walls on former Market building site. Preparations for extending work site boundary on Hadden Street to south side pavement on 21 October 2024.

 

Project Works – Beach

Boundary fencing erected around the beach and Broadhill sites. Site compounds and facilities established. Upgrading works on Broadhill path network underway. Boulevard closed off to traffic between Links Road and Esplanade with no issues.

 

Engagement and communications

Following Market stakeholder meeting and implementation of temporary traffic order, additional lighting and CCTV has been installed in Hadden Street to cover the footway area. Additional signage to signpost local businesses is being installed and will be in place when the Hadden Street site boundary is extended on 21 October 2024.

These measures have been communicated to local businesses directly and via the Generation Aberdeen website. In addition, Kirstie Golightly, public liaison manager for main contractor Morrison Construction, has been engaging directly with businesses and residents to assist with queries around traffic management, deliveries and parking.

Kirstie Golightly has also been engaging directly with businesses around the Union Street Central area on queries around access and deliveries. An on-going issue with food delivery cyclists and other cycle users ignoring the one-way system on Union Street has previously been raised with Police Scotland and is being monitored.

Additional Open for Business signage has been added to the Union Street Central hoarding with marketing materials distributed to businesses in the area. Radio and bus advertising to promote Open for Business is continuing across the city and shire.

For the beach projects, David Kindness, community liaison manager for main contractor Robertson Construction, has been engaging directly with local businesses about the setting up of the sites and the temporary closure of the Beach Boulevard between Links Road and the Esplanade. Details were also publicised via a letter drop to businesses and residents, on social media and via the Generation Aberdeen website.

Going forward, the Open for Business campaign will be extended to the beach area and stepped up for both Union Street Central and the Market.

Bus priority measures introduced by Aberdeen City Council in 2020, in line with the City Centre Masterplan goal of increasing sustainable travel, were made permanent at a meeting of the full Council on Friday 10 October 2024. A ban on vehicles making right turns from Union Terrace on to Rosemount Viaduct was lifted.

The bus priority measures from the Adelphi on to Market Street have been temporarily lifted for the duration of the new Market construction, which will allow vehicles to access Shiprow and Virginia Street from Market Street.

 

 

Temporary traffic restrictions for new Market construction

Temporary traffic restrictions for Aberdeen’s Merchant Quarter will take effect from Monday 7 October 2024 to allow construction of the new Market.

The restrictions will be in place until 31 October 2025 and will involve temporary road closures, diversions and restricted access and parking for vehicles. These restrictions are necessary to allow essential works, some of which will involve large construction plant and is to ensure the safety of the public and the site workforce.

Access for businesses and residents will be maintained wherever possible and the diagram below outlines the restrictions that will be in place.

Hadden Street between Stirling Street and Market Street will be closed and the construction site boundary extended to include that area for essential works traffic. Pedestrian access to businesses in Hadden Street will be maintained. Hadden Street will remain open to vehicles between Stirling Street and Correction Wynd.

The Green will be closed with access only for works traffic and authorised delivery vehicles. There will be parking restrictions on Rennies Wynd. Parking restrictions may be required at times for construction purposes in Carmelite Lane and Imperial Place but advance notification will be given.

Anyone requiring further information can contact the project team directly on streetscape-market@morrisonconstruction.co.uk.

Next stage of improvement works will see temporary closure of Beach Boulevard

A temporary closure of the Beach Boulevard between Links Road and the Esplanade will take place from 6pm on Sunday 29 September 2024 as part of the City Centre and Beachfront Masterplan.

This closure is to allow work to begin on the sites for the new beach park and events field by the main contractor, Robertson Construction Group. The area will be fenced off to allow construction to be carried out safely.

Clearly signposted diversion routes via Links Road and the Esplanade will be in operation. Two-way traffic on the Esplanade past the Queens Links Leisure Park will continue. The temporary closure will remain in place until the beach park and events field works are completed in 2026.

These works will be the biggest redevelopment of the beach area for 35-years and are part of a £50 million programme to create a transformational waterfront destination which will benefit businesses, residents and visitors.

The beach park will include an iconic play feature, the Rope Factory, which was developed through workshops with local school children and young people and was inspired by the city’s rope making heritage.

The events field will have an amphitheatre and will be able to host festivals, larger concerts and gatherings.

Other works being carried out at the beach include the upgrading of Broadhill, one of Aberdeen’s best known landmarks, and the demolition of the former beach leisure centre.

Planning application lodged for Queen Street urban park

A planning application for a £15 million urban park in Queen Street has been made by Aberdeen City Council.

The park would be a key element in the redevelopment of Queen Street, which is part of the council’s City Centre and Beach Masterplan to transform Aberdeen.

It will include outdoor seating, informal performance spaces, a terraced garden, a sensory garden and enhanced street greening. The application follows several months of consultation with neighbouring organisations and other stakeholders.

The new park will be located on land on the other side of Queen Street from the former police headquarters building. Options for the former police building are currently being reviewed by the council.

Each space within the urban park will perform a range of environmental and social functions which will be categorised by the overarching themes of urban nature, community, heritage and arts and culture.

It will also improve pedestrian and cycle movement between the city centre and the beach.

It is also hoped that the new park will help encourage investment by the surrounding private buildings and landowners.

The planning application can be viewed via reference number 241111/DPP at Simple Search (aberdeencity.gov.uk).

Works begin on new Market frontage

Work to erect scaffolding on the front of the former British Home Stores building in Union Street, Aberdeen, will begin on Monday 16 September 2024.

The works form part of the new Market project, which is a key element of the City Centre and Beach Masterplan (CCBMP) to transform Aberdeen.

Part of the south walkway in central Union Street, directly in front of former BHS building, will be closed off to the public for five days during the scaffolding works.

The public will still have full access to the shops and services on the south walkway on either side of the closure. JD, the Aberdeen Gift and Tourist Shop, Aberdeen Vinyl Records and the HSBC bank will still be open for business as usual from the west end of the walkway, as will Attic Clothing from the east side.

The scaffolding works are due to be completed on Friday 20 September 2024 and the walkway will be fully reopened as normal.

Masterplan projects continue to take shape, councillors told

Thursday 12 September 2024

Ambitious multi-million-pound projects which will completely transform the city centre and beachfront into vibrant attractions for local people and visitors alike are making significant progress, Aberdeen councillors were told today.

The update report presented at today’s Finance and Resources Committee meeting outlined a number of highlights over the last year in some of the high priority projects comprising the City Centre and Beach Masterplan (CCBMP) including the start of central Union Street public realm improvements, enabling works for the new market building, and the construction of the new Beach Park getting underway.

Aberdeen City Council Co-Leader Councillor Ian Yuill said: “Physical changes are now taking shape in the city centre and at the beach. These changes will play a key part in transforming the city centre and beach into even more attractive places to visit and spend time.

“The update at today’s Council meeting underlined the sheer scale of the projects – the biggest the city has seen in 200 years – and the Council’s continuing determination to make them a reality.”

Aberdeen City Council’s Finance and Resources Convener, Councillor Alex McLellan said: “Aberdeen City Council is delivering significant regeneration to our city centre and transformational investment at our beachfront to ensure our city continues to be somewhere people want to live, work, visit or invest.

“There are works now ongoing at Union Street, at the beach and at the former BHS site, which represents some of the biggest changes our city has seen in years.”

The update also highlighted the approval of an updated business case for public realm improvements on Union Street East, Union Street West, the West End, and Castlegate, alongside the delivery of the Union Street Empty Shops Action Plan which has seen a reduction in empty units thanks to £195,000 grant funding.
The report looked forward to the next stage of development which include:

• Construction of a 2.5 hectare Events Park and Broadhill enhancement as part of the £61.8million Beachfront

Phase A project;
• The anticipated completion of the Union Street Central Public Realm streetscaping by late summer 2025;
• Approximately 24 months of construction to deliver the new Aberdeen Market;
• Securing additional resources to further support the Union Street Empty Shops Action Plan;
• Completion of the new Beach Park by the end of 2025 / early part of 2026.

Biggest beachfront investment for 35-years about to get fully under way

The biggest redevelopment of Aberdeen beachfront for 35-years is about to get fully underway as part of Aberdeen City Council’s City Centre and Beach Master Plan.

Construction teams will begin work on three key sites next week as part of a £50 million programme to help make the beach area a must-visit destination.

Work will also shortly begin on stripping out the former beach leisure centre and detaching it from the adjoining Beach Ballroom before demolition proceeds. The Linx ice arena will remain open as normal during the works.

The major improvements will see the creation of a class-leading beach park, a large events field and the enhancement of the famed Broadhill in Phase A of the beachfront works.

Aberdeen City Council’s co-leaders welcomed the move as a key moment in the overall plan to make Aberdeen Beach a destination of choice for the public.

Co-leader Councillor Ian Yuill said: “Aberdeen Beach and the Links are a great asset for the city and wider North-east. The council is committed to working with beach users, partner organisations, and businesses at the beach to make Aberdeen Beach and the Links the envy of other cities and a place where local people and visitors alike will want to return to again and again.

“This new, exciting and high-quality development is the next step to make Aberdeen an even better place for residents and visitors to enjoy.”

Co-Leader Councillor Christian Allard said: “The start of the biggest redevelopment the beachfront has had for 35 years is an important milestone and we look forward to continuing to drive forward with our plans for transforming the beach area for the enjoyment of everyone.

“This investment in the beachfront is alongside the current redevelopment on Union Street Central and the new market building and these all have key roles in ensuring we have a vibrant and exciting city which will be enjoyed for generations.”

The main works can now begin as completion of diversion work on key underground services nears an end. A large gas pipe across the two sites has been diverted via Links Road along with work on water, electricity and broadband services around the boundary of the scheme.

The three sites will start to be fenced off from next week and the construction compound will follow on the former cricket pitch behind the beach leisure complex and the events field.

The beach park will include a play park, sports area/pump track, a gateway building, a hub building and a canopy shelter. The park will act as a key entry point between the city centre and the wider beach area.

A central feature of the play park will be the Rope Factory, a large-scale bespoke play structure, which is set to become an iconic beach attraction. This was shaped through workshops with Aberdeen school children and young people and was inspired by the city’s rope making history.

Within the play area there will be four zones – Sport, Adventure, Woodland, and Coastal – all with different activities in them.

The 2.5 hectare events field will be able to host festivals, larger concerts and gatherings. At its heart will be a 1 hectare flexible open area which can also be used as an informal space and will be semi-enclosed by woodland.

Broadhill is a beachfront landmark sitting between the Kings and Queens Links and offering outstanding views across the city and out to sea. The existing path network will be upgraded with improved surfacing along with viewing platforms and seating areas.

The biodiversity of the five-hectare Broadhill site will be enhanced with additional planting which will add to the distinctive natural environment of the area and increase habitat and ecological value.

During the works on the beach and events parks, the Beach Boulevard will be temporarily closed between Links Road and the Esplanade from the beginning of October with diversions clearly signposted.

The Broadhill works are due to be completed in the summer of 2025 while the beach and events parks are planned to be completed in 2026.

A site team will shortly begin separating and reconfiguring service connections between the Beach Ballroom, the ice arena and the adjoining former leisure centre. That will allow the strip out of the leisure centre followed by a start to demolition works. The demolition is expected to be completed by the summer of 2025.

The beach works are part of a £150 million commitment by Aberdeen City Council towards the City Centre and Beach Master Plan. Works are currently under way on streetscape improvements for the Union Street Central area while construction on the new market will begin this month. Public consultations have also been held for a new urban park in Queen Street and improvements to the Castlegate.

Works to progress on new market

Construction work on the new Aberdeen Market will progress this month with scaffolding erected to the front of the former British Home Stores building on Union Street and at the rear on the East Green during structural alterations.

To allow this work to be completed safely, the East Green between its junctions with the Green and Carnegie Brae will be temporarily closed to vehicles from 07:30hr on 16 September 2024 until 23:00hrs on 30 September 2025. Pedestrian access will be maintained at the rear of the properties on East Green.

The substructure work to install new ducting and drainage on the market site will also begin. This work may generate some noise and dust at times as it involves cutting and removing sections of the ground level concrete slab. The site team will have mitigation measures in place to minimise any impact during this work.

On completion of the drainage installation, work will begin to waterproof the existing ground level concrete slab and will continue until December 2024.

During these works, shops and businesses in the Green will remain open for business and access for the public will be maintained.

If you have any questions or would like more information about this project, please feel free to contact the site team via email at streetscape-market@morrsionconstruction.co.uk.

If you would like to receive email updates, for the work on the Aberdeen Market or/and Union Street you can sign up by emailing the site team at the above address. Alternatively, you can register your email address to be alerted when updates for any of the City Centre and Beach Master Plan projects are posted on the website, the registration section is at the bottom of the home page.

Consultation for Queen Street Urban Park

Plans are progressing to create a new urban park on land at Queen Street in the City Centre, following recent approval at Aberdeen City Council’s Finance and Resources Committee.

The redevelopment of Queen Street as a whole will create the opportunity to introduce new uses into the area, as well as new public spaces. The wider project will improve the amenity of the area and encourage economic and environmental sustainability in this key City Centre location. The Council’s investment in this space also aims to help stimulate investment from surrounding private building and landowners. Options for the redevelopment of the former Police HQ are being reviewed by the Council but the urban park, which will be on the land on the other side of Queen St from the former HQ, has approval to progress.

The Council’s design team are now finalising their designs for the urban park in advance of a planning application in September. This follows several months of detailed and constructive engagement with neighbouring organisations and other stakeholders.

The urban park concept includes provision for outdoor seating and informal performance areas, a sensory garden, terraced garden and enhanced street greening. Each space within the new urban park will perform a range of environmental and social functions, categorised into the overarching themes of urban nature, community, heritage and arts and culture.

If you would like to find out more about the proposals from the design team please come along to a drop-in event on Thursday 29th August, from 4pm to 7pm, at Aberdeen Arts Centre. There will also be the opportunity to comment on the proposals when a planning application is lodged in September.

Full consultation is available to view here: Queen Street Consultation Boards

Next stage of works to begin on Union Street Central

The next stage of works on Union Street Central are due to begin on Monday with the installation of a new drainage system.

This will involve removing old tram tracks which were buried below the existing road surface and removing small sections of the concrete slab. This process will generate noise and dust at times and measures will be taken to minimise the impact.

The drainage works are expected to take around six weeks and are expected to be completed by Friday 27 September 2024.

Once the drainage installation is completed, the remaining concrete slab will be removed and preparations will begin to install the new kerb area.

During these works shops and services in the Union Street Central area will remain open for business as normal and access for the public will be maintained.

Anyone who has any questions or requires further information about the works can contact the site team by email on streetscape-market@morrisonconstruction.co.uk.