Construction workers uncover hidden obstructions in Aberdeen’s Union Street

The construction team working on the £17 million transformation of Union Street in Aberdeen have revealed the hidden obstructions they have uncovered so far during the project.

Excavation work on the central section of the thoroughfare has encountered a series of unexpected underground obstacles which were completely uncharted.

From historic tram infrastructure to unrecorded utility pipes and cables or deep, hidden manholes, these discoveries have presented significant engineering challenges for Morrison Construction Infrastructure, who are the main contractor for the Aberdeen City Council development on Union Street.

One of the biggest hurdles for the team has been finding multiple layers of uncharted utility services buried beneath the road surface. These include clusters of electric cables, gas and water pipes, and other infrastructure that were previously undocumented on any maps or diagrams. More than 20 unrecorded clusters have been found so far across the site.

Uncovering these services means work cannot proceed as planned. Instead, gas, electricity and water organisations must be consulted and visit the site to determine whether the cables and pipes are still live and operational or redundant.

Live utilities must be made safe or moved and redundant services removed. This process is complex and time-consuming, adding unavoidable delays to the project.

Among the more unusual finds was an unknown capped off concrete access shaft which led down to a 10m deep underground culvert.

Due to the risk of collapse, the access shaft could not be safely removed. The project team then had to devise an alternative engineering solution to redesign the new street drainage system around this major obstacle.

In another striking historical find, workers uncovered old electric tram power cables encased in timber-framed wooden boxes which had been waterproofed and insulated with bitumen. Electric trams began operating in Aberdeen in 1899.

Eight of these tram power lines have been found running the length of the project site. The bitumen insulation, designed to protect against Aberdeen’s damp climate, highlights the durability and engineering ingenuity of the city’s historic tram network.

Further evidence of the tram system was also found, with old steel sleepers encased in concrete beneath the road surface throughout the site.

The site team also uncovered an 46cm diameter cast iron carrier pipe running the full length of the project area. Checks have been unable to confirm what the pipe was used for, but it is believed to be an old redundant water main, which then had to be removed to allow current construction to progress.

The presence of these unknown underground structures has impacted on the construction programme with time and resources having to be diverted to investigate, document, and, where possible, remove or work around them.

Before work began, pre-construction checks were carried out on the site, which included liaising with utility companies to confirm the location of services while ground radar was used to scan for any unexpected obstacles and trial pit holes were dug to investigate further.

However, these checks cannot guarantee to locate everything and sometimes services will remain undiscovered until the main excavations begin on site.

The improvement works cover a 300m section of central Union

Street and are divided into three 100m sections between Market Street and Bridge Street. Work began on the eastern section from Market Street and immediately started to find hidden obstructions.

Staff are currently working on the south pavement from Market Street and have encountered similar issues with one utility recorded on service maps, but another nine unrecorded services were then uncovered during excavations, including two gas pipes.

Given the challenges faced in the initial stages, the team have taken proactive steps to conduct advance excavation work in the western section of the site and deep trench investigations in the central section, helping to identify further potential clashes with uncharted utilities before the main construction phase began there.

While the roadway was exposed, the construction team also took the opportunity to install the new main carrier drainage pipe and associated chambers, ensuring that future works could proceed more efficiently.

Rod Buchan, construction manager for Morrison Construction Infrastructure on the project, commented: “Despite the challenges presented by these unexpected underground discoveries, the team remains committed to delivering the much-needed upgrades to Union Street Central.”

Hub North Scotland is Aberdeen City Council’s delivery partner for the City Centre and Beachfront Master Plan and project director John Edwards said: “The project team went to great efforts before works started to determine what lay beneath the ground.

“However, there is always a possibility of finding these uncharted obstructions which can be incredibly frustrating for the site team and can have an impact on progress. The team continue to work hard to minimise that for the shops and businesses.”

Aberdeenshire granite setts being produced for Union Street Central

Thousands of granite setts made from stone taken from an Aberdeenshire quarry are being produced for the new surfacing in Union Street Central.

The light grey setts are being provided to the City Centre and Beach Masterplan project from Moray firm Tennants Elgin Ltd.

It is estimated 1,000 tonnes of setts will be laid as paving on Union Street as a feature of the new surface, complementing the surrounding historic granite buildings as well as supporting a local North East business.

Huge granite boulders were blasted and then removed from Avochie Quarry near Huntly and taken to the firm’s Elgin site for cutting and finishing. The process involves cutting down the huge boulders with two different grades of stone saw and then taken inside for carving down to the blocks using smaller and more precise stone saws. Each boulder provides about 150 to 200 setts.

Gavin Tennant, managing director, explained Avochie Quarry is one of five owned by the family firm, and they are delighted that local granite will be used for a local project.

He said: “Our granite is very high quality, and we take care and pride in our work which takes the raw stone from our own quarries and then to Elgin to shape them into whatever size and shape is required for a particular project.

“We have an ongoing supply stone for the La Sagrada Família in Barcelona, and have provided stone for Oxford University, Edinburgh University, and St Andrews University and it’s good to finally have a project in Aberdeen.

“It’s not very often we get to see the product in its finished state, and we are honoured we will be seeing local granite setts on Union Street on Aberdeen and the small part we have played in that process.”

Aberdeen City Council Co-Leader Councillor Christian Allard said: “The Union Street works are taking place at the same time and are alongside the construction for the new market building so it will be an exciting moment when Aberdeenshire granite setts are placed on the surface.

“Alongside the city centre works which will also include the Castlegate after the Tall Ships event is finished, the beachfront is continuing to get its biggest redevelopment for 35 years. Once finished, these developments will make a major difference to the city.”

Aberdeen City Council Co-Leader Councillor Ian Yuill said: “The city centre and beach areas will be significantly improved through the agreed construction works. These are major investments to upgrade the city for the benefit of all.

“It is great to see a North East firm is providing the granite setts for Union Street Central. Selecting a local business that offers high-quality products is an important way to support our regional economy. This project is good for our area.”

Our video shows the stone being quarried at Avochie before it is crafted at Tennants Elgin base in preparation for transportation to the Aberdeen project site. The setts are due to be installed in the next few months.

Making a difference at the beach

The City Centre and Beach Master Plan is more than just building something.

Every construction project in the plan also has social impact and community benefit targets for the main contractor to meet.

These include job opportunities, apprenticeships, work experience, volunteering, and community donations.

At the beach project, our main contractor Robertson has been working hard, and their social impact team has already gathered some impressive figures as this infographic shows.

A video showing the latest works on the beachfront project

A video showing the latest works on the beachfront project.

Aberdeen City Centre and Beach Master Plan Update

14 March 2025

Project Works – Union Street Central

Works continue to progress well with the final concrete slab at the Market Street junction now in place. The concrete slab will provide the foundation for the new locally sourced granite setts to be installed.

The existing south footway at the east end of the site is being removed and a temporary pedestrian crossing near Attic Clothing has been installed to ensure access to businesses during this stage of the works.

The south footway works will see the installation of a new mains electric cable and other electrical and communications infrastructure before the new footway paving is installed.

A second temporary pedestrian crossing at Aberdeen Vinyl Records and the Aberdeen Gift and Tourist Shop will also be in operation from Monday 17 March as works continue across the site.

Over the coming weeks, construction teams will install 50% of the new kerb log in the central section of the site and begin laying the first of the new concrete slabs.

Project Works – Market

Key structural and restoration activities continue at the Market site. The new steel frame roof structure for the former British Homes Store building at 91-93 Union Street is now in place and additional streel frame installation work remains a key focus and is progressing well.

Significant progress has been made on the new in-situ walls for the main market building and the formation of new service pits is moving forward.

Over the next two weeks the steel frame installation at 91-93 Union Street should be completed and ongoing concrete remedial works finalised. Key drainage preparations and structural improvements will continue.

During April it is planned to begin installing the outer curtain walling frame on the frontage of 91-93 Union Street.

 

Project Works – Beachfront

Cut and fill works across the site are now complete along with main drainage and localised drainage well progressed.

From Monday 17 March work will being to pour the concrete foundations for the amphitheatre and the beach park gateway building. At the same time work will begin on forming and shaping the new skate park.

Work to install a second line of new steps providing access to the top of Broadhill are progressing well along with the new paths and viewpoint network.

 

Project Works – Castlegate

Final design works are continuing to progress for the Castlegate streetscape improvements. The construction team will move on site to begin works at the beginning of August 2025  following the visit of the Tall Ships race to Aberdeen.

Fly through video shows Union Street Central after works complete

A fly through video has been released showing how Union Street Central will look following the completion of the current works.

‘The video shows how buses, cyclists and pedestrians will interact and the completed paving using locally sourced granite and Scottish whinstone.’

Union Street Central Public Information Event

The contractor working on the Union Street Central project is holding a public information event about the construction works this Thursday, 6 March 2025.

Morrison construction is hosting the event at the Douglas Hotel in Market Street from 2pm to 6pm.

Members of the public can come along and meet the site team, hear the latest progress updates and ask questions.

Anyone who cannot attend can contact the site team by email on streetscape-market@morrisonconstruction.co.uk .

Union Street Central Works Update

24 February 2025

 As part of the works to upgrade the south footway on Union Street Central, this week the contractor will be replacing the metal solid hoarding on the south alignment with Heras fencing.

The metal hoarding on the north side of the works area will be extended further west to replace Heras fencing currently in place there.

Two temporary pedestrian crossings will be installed to enable pedestrians to access shops and businesses on the south footway. The first pedestrian crossing will be in place from 10 March across Union Street, directly opposite the Attic clothing store, and will be in operation during the works. A second pedestrian crossing will be installed later that week, directly opposite Aberdeen Vinyl Records and the Aberdeen Gift and Tourist Shop.

Construction work on the south footway is planned to begin on Monday 3 March at the Market Street junction. This will involve lifting the current slabs, removing any redundant services, installing drainage, new electric service cabling and ducting, back filling the area and installing a layer of tar ahead of and installing the new footway paving.

Access to shops and premises will be maintained during business hours. All footway works in front of shop and business entrances will be carried out overnight, outside business hours. Authorised vehicles will continue to travel west to east along Union Street Central.

Kirstie Golightly, stakeholder manager for the works contractor, Morrison Construction, will be visiting businesses located along the works area as required to keep them informed of progress and to assist with any queries.

Aberdeen City Centre and Beach Master Plan Update

19 February 2025

Project Works – Union Street Central

At the east end of the construction site at the Market Street junction we have relocated hoarding panels, removed the existing traffic signal post and installed new technology ducts.

In the central section of the site, we have been investigating uncharted services and have now fully removed the remaining carriageway surface. Progress continues with 80% of the new carrier drain installed and 30% of the concrete foundation complete.

Over the next two weeks we will complete the final concrete slab at the east end of the site and will install a temporary pedestrian crossing on Union Street to maintain access to shops and businesses while we begin removing the pavement on the south side at the Market Street end.

Work will also begin on relocating the solid hoarding panels from the south footway at Market Street to the north side of the central section of the site. We will also start installing new road gullies and kerb logs in the central section.

Project Works – Market

Internal drainage works are progressing along with the construction of new concrete service pits for the escalators and lifts. Remedial works on existing concrete structures continues along with the construction of new retaining walls. Waterproofing is underway for both the service pits and the retaining walls.

The remedial works, wall construction, serviced pits and water proofing will continue over the next two weeks and the former British Home Stores building will be cleared in preparation for the installation of a new steel frame.

 

Project Works – Beachfront

Ground works are continuing across all parts of the project site with precast steps being installed on the Broadhill along with the continued upgrading of the existing path network and the creation of new paths and viewpoints.

Work has started on creating a new temporary car park at the rear of the existing ice arena and will continue over the next four weeks. The arena will remain open as normal during all the project works.

Drainage works on the new events field are continuing and drainage works for the beach park are due to commence.

 

Project Works – Castlegate

Final design works are continuing to progress for the Castlegate streetscape improvements. The construction team will move on site to begin works at the beginning of August 2025  following the visit of the Tall Ships race to Aberdeen.

Exciting new brand unveiled for Aberdeen Market

The new Aberdeen Market building, which is currently under construction on Union Street, has revealed its new identity.

The McGinty’s Group, the chosen operator for the Aberdeen City Council’s venture, has revealed the venue will be called FLINT.

Proudly linking back to the site’s prehistoric past as a location for ancient tool-making craft, the name pays homage to the rich legacy of flintknapping which was carried out at The Green around 8000 years ago.

Construction work is underway at the site with the new market due to open in 2027. The project is a key part of Aberdeen City Council’s City Centre and Beach Master Plan which will see the biggest redevelopment in the city centre since Union Street was built 200 years ago.

Set to revitalise The Green area, FLINT will house international-style food and drink outlets from local vendors and artisan traders with a vibrant food hall inside. The destination venue will also have a large outdoor area for pop-up markets and other events and will boast improved connectivity between the bus and rail station to Union Street.

Martin Widerlechner, who is McGinty’s marketing director for Flint, said: “The name reflects the spirit of ingenuity and resilience that is a hallmark of the Granite City. The new branding connects the past and the future and hopefully will ignite the regeneration of this great city.”

He added: “We took our time with this process as we understand the importance of the project to the city. We received nearly 400 suggestions from the public and it was tough to choose the best, but Flint stood out the most. We will be revealing more about the name, the branding and the market over the coming months.”

Aberdeen City Council’s co-leader, councillor Christian Allard, said: “Flint is an excellent choice of name for the new market building which will play a key role in making Aberdeen’s city centre a world-class destination for residents and visitors to enjoy.”

Co-leader, councillor Ian Yuill, said: “The new market will add much vitality and attract more visitors to the city centre. The council’s investment in this project and in other improvements, such as the upgrades in central Union Street, will help to make the city centre a more vibrant and desirable destination for everyone. The name Flint highlights that this is the historic centre of Aberdeen, and the various initiatives will ensure that this area will remain at the heart of city life.”

The new market name was inspired by the discovery on The Green in 1976 of tiny blades of local honey-coloured Buchan flint, which suggested craftsmen had worked on the site around 8000-years ago.

More details on Flint can be found by following FlintABZ on Facebook, Instagram and LinkedIn and on the website www.flintabz.com .

Alongside the new market building, Aberdeen City Council are also redeveloping the streetscape on Union Street Central to make it more accessible and welcoming along with major works at the beachfront which include a class-leading beach park, an events park and improvements to the Broad Hill.