Demolition works to begin at former beach leisure centre

25 September 2025

 

The demolition of the former beach leisure centre will begin next week. Preparations are already under way with part of an external wall removed to allow specialist machinery access into the building.

 

Site operatives will strip out internal fixtures and fittings and dismantle the swimming pool external flumes. Solar panels on the roof will be removed and retained for reuse or recycling.

 

Work will then begin on removing the former gym hall and the link bridge to the Beach Ballroom before the main demolition works begin.

 

Most of the demolition should be completed before Christmas and the site will be cleared in early 2026.

 

The Linx Ice Arena will be open as normal, and the demolition works will not affect any part of its operation.

New market building starts to take shape

As the steel work erections progresses on the new Aberdeen Market building, the shape of the building is beginning to become clearer.

These photographs show how the building, to be called Flint and operated by local hospitality group, McGintys, will be a prominent landmark in the city centre.

Main contractor, Morrison Construction is progressing well with the works, which are on programme.

The steel being used for the development is being supplied by local business, KR Group from Newburgh in Aberdeenshire, as part of the commitment to use local suppliers whenever possible.

The market is a key part of the £150 million City Centre and Beach Master Plan being delivered by Aberdeen City Council

Temporary traffic restriction on Belmont Street at Union Street

Traffic will not be able to enter or leave the Union Street end of Belmont Street from next Tuesday (23 Sept 2025) to allow for reconstruction as part of the upgrade works to Union Street Central.

The temporary restriction is from Tuesday 23 September 2025 until Sunday 22 March 2026 and there will be no entry from Union Street onto Belmont Street, and no exit from Belmont Street onto Union Street.

Access to properties will be maintained however no through-traffic will be possible during this time. An alternative route for vehicles is available via Union Terrace, Rosemount Viaduct, Schoolhill, Back Wynd and Little Belmont Street and Gaelic Lane.

The diversion route includes:

  • At the end of Little Belmont Street and Gaelic Lane, all vehicles must turn right onto Belmont Street. A left turn will not be permitted
  • All other vehicles must then exit Belmont Street and via Schoolhill

 

To facilitate this diversion, Little Belmont Street will be temporarily reopened to through-traffic and planters and stone roadblocks on Little Belmont Street will be removed. They will be reinstated once the diversion is no longer required.

Vehicles to drive on first phase of Union Street Central Works  

The first phase of the Union Street Central Streetscape works will be open to permitted vehicles from today.

Traffic is being switched over to the new granite setts road surface on the east section of the works, between Correction Wynd and St Nicholas Street.

That will allow work to begin on the existing road surface on the north side of the street. It will become part of a widened and enhanced new pavement area.

Permitted vehicles currently allowed to use the new section are taxis, delivery vehicles during approved times, and cyclists, all travelling one-way, west to east along Union Street Central. Emergency vehicles will continue to always have access.

Pedestrians will continue to have access to businesses and premises on the north side of Union Street during the latest works.

The new road surface is made from local granite sourced from the Avochie quarry in Aberdeenshire and manufactured into traditional setts by Elgin family business Tennant.

John Edwards, project director for hub North Scotland, who are the council’s development and delivery partner for the City Centre and Beach Master Plan, said: “This is a landmark moment for the Union Street Central streetscape works with the first traffic running on the new road surface.”

He added: “The first phase of these works has proved more challenging than expected, despite the thorough surveys undertaken, with the discovery of many unrecorded utility services and other hidden obstructions which has seen the site team having to come up with different solutions.”

The main contractor for the works is Morrison Construction Infrastructure and the site team are also progressing in the central section of the project area. The works are due to be completed in Spring 2026.

Alongside Union Street Central, work is continuing on the new Aberdeen Market, which will be called Flint, and is due for completion in 2027. The main contractor for that part of the Master Plan is Morrison Construction North-east.

The new beachfront works are also progressing with main contractor Robertson Construction already completing the Broadhill enhancement while the new beach park and event park are well under construction.

First stage of £50 million beachfront redevelopment officially opened

Cllr Martin Greig, the Lord Provost Dr David Cameron, Richard Park, chief executive of hub North Scotland, and Elliot Robertson, Chief Executive Officer, Robertson Construction Group, with some of the Young Ambassadors in the background, on one of the viewing platforms at the new-look Broadhill

The first part of a £50million redevelopment of Aberdeen beach was officially opened today with the unveiling of the new-look Broadhill.

Aberdeen’s Lord Provost, Councillor David Cameron, toasted the occasion with a cup of tea from a tartan flask and a traditional rowie at a striking new viewpoint on top of the well-known landmark.

The five-hectare Broadhill has been transformed with new access steps, footpaths, viewpoints, drystone walls, timber and concrete seating and landscaping. The work has been completed in time for the public to enjoy the site as a vantage point for the forthcoming Tall Ships Race (19-22 July).

As he surveyed the completed works, the Lord Provost said: “This is an exciting occasion to toast with the first part of the beachfront works finished.

“As thousands of people come into the city for the Tall Ships Races, the revamped Broadhill with additional seating and a viewpoint will be a prime place to watch the vessels sail into the harbour as well as the spectacular Red Arrows display.”

Broadhill is part of the biggest redevelopment of Aberdeen beach for 35 years with work well under way in creating a beach park and a large events field.

The Broadhill works have seen more than 10,000 new trees, shrubs, and underlying vegetation planted across the site to help enhance the natural environment by further diversifying the habitat and ecological value of the area.

The Lord Provost was joined for today’s opening ceremony by members of the city’s Young Ambassadors, a group of young people who contributed ideas for the beach plans.

Aberdeen City Council’s Co-Leaders welcomed today’s opening as the first project to be completed in the ambitious Aberdeen City Centre and Beach Master Plan.

Co-leader Councillor Ian Yuill said: “It is good to see the first of the beach works finished as the first of the City Centre and Beach Master Plan projects.  We hope many generations to come will make good use of the changes at Broadhill. The beachfront is one of the jewels in the city’s crown and the work taking place in the area will further transform the beach area for the enjoyment of everyone.

“The works are the biggest redevelopment the beach has had for 35 years and is the next step to make Aberdeen an even better place for residents and visitors to enjoy.”

Co-leader Councillor Christian Allard said: “We welcome the works finishing at Broadhill. As work continues at the beach, I am looking forward to more of the works finishing and people of all ages being able to make use of the great new facilities.

“We welcome the input of the Young Ambassadors who helped to shape the new facilities here at the city’s beach.  The Council is committed to working with Aberdeen’s residents, beach users, partner organisations, and businesses at the beach to make Aberdeen beach and the Links the envy of other cities and a place where local people and visitors alike will want to visit to again and again.”

The other beach works have seen five new buildings and shelters currently being constructed for the play and events sites along with a new skate landscape while the foundations have been laid for a large bespoke play structure called the Rope Factory which is set to become an iconic attraction.

The play area will have four zones – sport, adventure, woodland, and coastal – all with different free activities.

The 2.5-hectare events field will have an amphitheatre and will be able to host festivals, larger concerts and gatherings. The play park and events field are due for completion in Autumn 2026.

Hub North Scotland is the council’s development and delivery partner for the master plan projects and the main contractor for the beach works is the Robertson Construction Group.

Richard Park, chief executive of hub North Scotland, said: “This is a landmark moment for the beach redevelopment with the transformation of Broadhill and the progress on the other works. Robertson has done a fantastic job in completing the Broadhill and every day now you can see the progress on the rest of the area. This will be a ‘must-visit’ destination when completed.”

Elliot Robertson, Chief Executive Officer, Robertson Construction Group, said: “The opening of Broadhill is the first completed project as part of the overall transformation of Aberdeen’s beach. Being the trusted delivery partner, we understand the importance of bringing the vision of Aberdeen City Council and the local community to life.

“Working closely with hub North Scotland and the Council, significant progress is being made in the creation of well-designed, connected spaces which will be home to high-quality facilities. The vision to redevelop the beach will benefit the community through the provision of public realm spaces that will inspire wellbeing and activity and contribute to the local and regional economy.”

Work is progressing on stripping out the former Beach Leisure Centre in preparation for demolition of the building, which is due to begin next month. The Linx Ice Arena is open for business as normal during the works.

The beach improvements are part of a £150million commitment by Aberdeen City Council towards the City Centre and Beach Master Plan. Works are well under way on a new streetscape for the Union Street Central area while construction on the new market building is progressing as planned. Work is also due to begin on new streetscape improvements to the Castlegate next month. These areas will create vibrant and accessible areas to help make the city a destination of choice for the benefit of residents, visitors, and businesses.

Aberdeen City Centre and Beach Master Plan Update

2 July 2025 

Project Works – Union Street Central

The transformation of Union Street Central continues with progress across the east and central sections of the site.

The site team have started laying the granite setts in the east section of the main carriageway which will give this area its distinctive finish.

The south footway works between Market Street and Attic are nearing completion with the new kerb line almost complete and 99% of the paving slab in place. The delineator trims, which mark the changes in surface use are fully installed and the drainage weepholes in the road surface have been completed.

The south footway from Attic to the HSBC cash machine has been excavated and refilled, while protection works over former coal chutes below the surface have been completed.

In the central section of the site, all preparations for new street furniture are complete and the sub-surface has been laid along that stretch of the south footway. New kerbs and delineator trims have been laid along most of the section, providing a clear outline of the final upgraded layout.

Over the next few weeks, the final kerbing and paving in the east section will be completed with a final protective layer between Attic and HSBC. The site team will also complete laying kerbing and delineator trims in the central section before commencing installing the granite setts.

 

Project Works – Market

All scaffolding has now been removed from the front and rear of the former British Homes Stores building at 91-93 Union Street and basement substructure works are well underway to form the foundations for future internal features.

Construction of the in-situ concrete walls which will form the core of the new market building is continuing to progress and will be brought to completion during July.

At the Market Street end of the site, excavations and service diversions are in progress to prepare for the foundations which will support the Market Street Arch. These excavations revealed several uncharted utility services which required additional co-ordination and minor adjustments to planned works.

Preparations are underway to install pre-cast concrete stairs, in addition to the planned escalators, within the main market building and towards the end of July the team expect to begin installing the steel frame for the new market building.

 

Project Works – Beach

The steelwork for all five new buildings on the beachfront site has now been completed and construction teams are progressing joinery and other works on the structures. These include installing water infrastructure for toilets in three of the buildings and drinking fountains across the site.

All the utilities connections to the site have been completed and the traffic restrictions on roads around the site have been lifted. Only minor tidying up work remains on the Esplanade.

Work on the new skate landscape is well progressed with some of the features, such as the large bowl area now completed. The foundations for the play park equipment have also been completed.

The main Rope Factory structures are currently being fabricated in Scotland and should be ready for installation later in the summer.

The final Broadhill works are being completed in time for it to be ready and open to the public for the Tall Ships visit.

Internal soft strip works at the former Beach leisure centre are progressing with the aim to start the demolition of the building at the end of July or early August.

 

Project Works – Castlegate 

Scaffolding was erected around the Mercat Cross to undertake a detailed inspection and condition survey.  The team will remove the scaffold and install information panels for the Tall Ships visit. The cross was originally built 339-years ago, and specialist conservation architects have been appointed to assess its condition and look at restoration options.

Further engagement events to outline the streetscape improvement plans have been held with the Disability Equity Partnership, the Aberdeen Cycle Forum as well as local businesses. These sessions were positive, and the points raised by all groups have been fed back to the project team and actioned.

Following the Tall Sips events, the Castlegate site team will begin preparations in August for the streetscape works which are expected to be completed in the summer of 2026.

Aberdeen city Centre and Beach Master Plan Update

6 June 2025

 

Project Works – Union Street Central

Works have been completed on the south footway between Market Street and Attic with redundant services removed and new paving and kerbing installed.

 

Underground electrical and communications service infrastructure has been fully installed along the south footway, which will allow surface works to advance in the coming weeks.

 

Kerb installation for the new cycleway will continue to progress and the remaining street furniture bases will be installed.

 

New tarmac surfacing will be laid in the coming weeks followed by further paving slab installation to further shape the new look and feel of Union Street’s central area.

 

 

Project Works – Market

Work has been progressing on new concrete walls which will form the structural core of the market building. These works include extensive waterproofing against weather exposure.

 

The new standing seam roof at 91-93 Union Street, formerly British Home Stores has been completed, which allow internal fit out works to begin shortly.

 

Work to remove the scaffolding on the front of 91-93 Union Street is expected to begin week commencing Monday 9 June and should be completed within 10-days. Once that is done, work will begin to remove the scaffolding from the rear of the building.

 

That will allow basement substructure works to commence and prepare the area to receive new pre-cast concrete stairs within the main market building.

 

Preparation works to lay new foundations for the new Market Street arch will also begin. This feature will incorporate reclaimed granite stone from the original shopfront which linked the old market building to neighbouring properties. It will visually tie the new structure back into its surroundings in a way that respects and helps preserve and echoes the original character of the historic layout.

 

 

Project Works – Beach

Works on the beachfront area are progressing on programme with the Broadhill improvement project due to be completed and handed over next month.

Steelwork has also been erected for two of the new buildings – the Gateway Canopy and the Play Park Canopy., and work will continue to progress those structures.

 

On Monday 9 June the internal soft strip works will begin at the former beach leisure centre. Once that is completed the structural demolition of the building will commence later in the summer.

 

The upgrade of the rear car park at the Linx Ice Arena has been completed and is due to come into use on Thursday 12 June. The existing front car park will be closed with hoarding erected around it as it becomes part of the works site.

 

The skate landscape is taking shape with a team from the specialist contractors, Betongpark, on site supervising operations with the first concrete already poured. All the team are experienced skaters, and the company is recognised as one of Europe’s leading exponents of skate area design and construction.

 

Work is also progressing on utility service connections to the site and is due to be completed school summer break.

 

 

Project Works – Castlegate

 

Initial ground site investigation works on the Castlegate have been completed and the findings will be assessed to help inform the programme of streetscape improvements for the area.

 

Engagement sessions were held at the Salvation Army Citadel with businesses located on the Castlegate and Justice Street to go over how the street area will operate once the improvements are completed. The sessions were well attended with positive feedback and the points raised will be looked at by the project team.

 

The streetscape works are due to begin in August following the Tall Ships Race events and are expected to be completed in the summer of 2026.

Roof works completed at Union Street entrance to the new Aberdeen market

A new roof for the former British Home Stores building on Union Street has been completed as part of the works for the new Flint Market development in Aberdeen.

A steel frame has also been constructed in the building at 91-93 Union Street, which will be one of the main entrances to Flint. Work is now progressing on installing curtain walling, which lets natural light into the building while keeping the elements out.

The scaffolding erected on the Union Street frontage of the building last September will be removed next month as part of the works. That will allow work to begin on installing a canopy over the Union Street entrance.

The £40 million market development is a key part of Aberdeen City Council’s £150 million City Centre and Beachfront Masterplan, which is the biggest redevelopment of Aberdeen in 200 years.

The latest progress was welcomed by Aberdeen City Council co-leader, Councillor Christian Allard and Councillor Martin Greig, Vice-convenor of the Planning Development Management Committee, who said the new market will be crucial in helping revitalise and transform the city centre.

Councillor Allard said: “Today marks an important milestone for our city centre. The new Flint Market development is really starting to take shape, bringing with it the promise of enhanced amenities – and yet more reasons to visit Aberdeen’s heart. By investing in infrastructure, we are creating the conditions for growth.”

Councillor Greig said: “These are enormously exciting times for Aberdeen. As well as the new Flint Market and streetscaping on Union Street Central, the Council is transforming the beach area and is set to rejuvenate the Castlegate as a public space. The Tall Ships event in July will only add to today’s sense of momentum.”

Hub North Scotland are the council’s development partner for the City Centre and Beachfront Masterplan and market project director John Edwards said: “A huge amount of work has gone into reaching this stage and the progress will become even more visible over the coming months to deliver a landmark the city can be proud of.”

Colin Milne, framework director for Morrison Construction, who are the main contractor for the market, said: “We’re delighted to have completed these early works of this key regeneration project in the heart of Aberdeen. As the project continues to take shape, we look forward to working closely with the Council, Hub North Scotland, and our local supply chain to bring the Flint Market vision to life.”

New reinforced concrete walls are being constructed on the site on the Green and service pits for escalators and lifts have been completed. The plaza area adjoining the building is also being prepared. The main steelworks for the new building are due to begin this summer.

Work is also underway for major sewer connections on Carnegies Brae, which will then allow the market to be connected to the district heating network via new pipes being laid from the council’s headquarters at Marischal College.

Aberdeen hospitality business, McGinty’s Group, will be the operators of Flint when it opens in 2027. The development name was selected to reflect the site’s past and its future. Around 8,000-years ago it was a hub for flint working and the new market building will have a honey-coloured roof.

Temporary traffic management measures for beachfront project works

Temporary traffic management arrangements will be implemented at Aberdeen beach from Monday 12 May to allow crucial works on the beachfront regeneration project.

A phased series of restrictions will enable new utility services on the project site to be safely connected to the city’s utility infrastructure network under the surrounding roads and paths.

These works have been planned to keep disruption to a minimum and will be completed before the school summer holiday break. The restrictions will be as follows:

  • Monday 12 May to Wednesday 4 June: Links Road southbound at the Beach Boulevard will be closed. There will be a left turn only from the Beach Boulevard northbound and a left turn only from Links Road northbound
  • Thursday 5 June to Friday 6 June: Links Road between the Beach Boulevard and Cotton Street will be closed both ways
  • Monday 9 June to Wednesday 11 June: Links Road at the Beach Ballroom will be closed both ways
  • Thursday 12 June to Friday 29 June: Links Road at the Beach Ballroom will have parking restrictions and a footpath closure
  • Monday 30 June to Friday 4 July: The Esplanade from the Beach Boulevard to Innoflate will have parking restrictions and two-way traffic lights at times

Sign posted diversions via the Esplanade/Links Road and/or the Beach Boulevard will be in place for the duration of the works.

Access to all local businesses and premises will remain throughout the works and all car parks can be accessed via the diversions.

The works are part of the £50 million redevelopment to make the beach area a must-visit destination. The improvements include a class-leading beach park, a large events field, and the enhancement of the Broadhill.

Investigation works to begin at the Castlegate

Preliminary investigation works for the Castlegate streetscape improvements will begin on Monday 5 May and will continue until Friday 23 May 2025.

These will involve digging small, shallow trial holes to help locate buried utilities or unexpected ground conditions. There will also be a small number of boreholes to help assess soil layers and deeper ground conditions.

These activities will take place between 8am and 6pm, Monday to Friday. Disruption will be kept to a minimum and the investigation areas will be fenced off.

Access will always be maintained to homes, businesses, and shops.

These investigations are essential to prepare for the main construction phase of the works, which are due to begin following the Tall Ships Race at the end of July.

The £150million commitment by Aberdeen City Council towards the City Centre and Beach Master Plan includes major improvement works underway at Union Street Central, the new market building, and at the city’s beach area, as well as the Castlegate streetscape improvement works to come. They will create vibrant and accessible areas to help make the city a destination of choice for the benefit of residents, visitors, and businesses.