Castlegate Streetscape works update
Following a site meeting with utility services representatives on the Castlegate, we can now confirm the following position on works due to be carried out:
- The excavated area on the north side of the Castlegate outside Gio’s by La Lombarda will be temporarily reinstated with work beginning today and ready on Thursday 6 August for outdoor seating once the fencing has been realigned to accommodate the new footpath and backfilled area
- Access to Siam Cottage will remain with temporary solutions put in place when required
- Additional Open for Business and access signage will be implemented by the site contractor and hub North Scotland
- The BT Openreach works on the south side of the Castlegate will begin on Monday 17 August
- Pedestrian access to all shops and premises will be maintained as currently in place during the utility services works
- Extended footpath and associated works will begin on Thursday 6 August and are anticipated to be completed by Friday 14 August
Further updates on the progress of these works will be posted on this news page.