Aberdeen city Centre and Beach Master Plan Update
6 June 2025
Project Works – Union Street Central

Works have been completed on the south footway between Market Street and Attic with redundant services removed and new paving and kerbing installed.
Underground electrical and communications service infrastructure has been fully installed along the south footway, which will allow surface works to advance in the coming weeks.
Kerb installation for the new cycleway will continue to progress and the remaining street furniture bases will be installed.
New tarmac surfacing will be laid in the coming weeks followed by further paving slab installation to further shape the new look and feel of Union Street’s central area.
Project Works – Market

Work has been progressing on new concrete walls which will form the structural core of the market building. These works include extensive waterproofing against weather exposure.
The new standing seam roof at 91-93 Union Street, formerly British Home Stores has been completed, which allow internal fit out works to begin shortly.
Work to remove the scaffolding on the front of 91-93 Union Street is expected to begin week commencing Monday 9 June and should be completed within 10-days. Once that is done, work will begin to remove the scaffolding from the rear of the building.
That will allow basement substructure works to commence and prepare the area to receive new pre-cast concrete stairs within the main market building.
Preparation works to lay new foundations for the new Market Street arch will also begin. This feature will incorporate reclaimed granite stone from the original shopfront which linked the old market building to neighbouring properties. It will visually tie the new structure back into its surroundings in a way that respects and helps preserve and echoes the original character of the historic layout.
Project Works – Beach

Works on the beachfront area are progressing on programme with the Broadhill improvement project due to be completed and handed over next month.
Steelwork has also been erected for two of the new buildings – the Gateway Canopy and the Play Park Canopy., and work will continue to progress those structures.
On Monday 9 June the internal soft strip works will begin at the former beach leisure centre. Once that is completed the structural demolition of the building will commence later in the summer.
The upgrade of the rear car park at the Linx Ice Arena has been completed and is due to come into use on Thursday 12 June. The existing front car park will be closed with hoarding erected around it as it becomes part of the works site.
The skate landscape is taking shape with a team from the specialist contractors, Betongpark, on site supervising operations with the first concrete already poured. All the team are experienced skaters, and the company is recognised as one of Europe’s leading exponents of skate area design and construction.
Work is also progressing on utility service connections to the site and is due to be completed school summer break.
Project Works – Castlegate
Initial ground site investigation works on the Castlegate have been completed and the findings will be assessed to help inform the programme of streetscape improvements for the area.
Engagement sessions were held at the Salvation Army Citadel with businesses located on the Castlegate and Justice Street to go over how the street area will operate once the improvements are completed. The sessions were well attended with positive feedback and the points raised will be looked at by the project team.
The streetscape works are due to begin in August following the Tall Ships Race events and are expected to be completed in the summer of 2026.












